Tipos de produtos usados | Auxílio de Fluxo , Canhões de Ar |
---|---|
Indústria | Usinas Termelétricas |
cliente | Bay Shore Station, FirstEnergy Corporation Oregon, Ohio |
Problema
This 631 MW power plant uses petroleum coke – a refinery waste product – to fire its boilers. But the sticky material would build up on the walls of the chutes carrying it from the gravimetric feeders to the boiler. Instead of the 300 tph required, the feed rate would slow down to 75 to 100 tph, starving the boilers.
The plant staff resorted to frequent cleaning of the chutes. But even after a cleaning, material would begin to build up almost immediately and the chutes would begin to choke again. Within one eight-hour shift, the feed rate might be reduced to 75 to 100 tph again.
Solução
Resultados
The Martin® Air Cannons are discharged in a cycle that calls for the two bottom cannons on a given chute to be fired together, with progressively higher air cannons fired individually at five-second intervals. After all cannons on a given chute are fired, the cycle moves to the next chute. After installation of the Martin® Air Cannons, the feeder system is operating as designed. The boiler unit has not tripped due to fuel shortage resulting from plugged feed chutes since the air cannon installation.
Resolvemos o seu problema!
Com mais de 70 anos de experiência resolvendo problemas em todo mundo com os profisisonais mais experientes e educados em nossas equipes, podemos assegurar-lhe que ficaremos perto o suficiente para saber o que precisa ser feito em seguida e resolver o seu problema.
Deixe-nos lhe mostrar a solução.